Case study 01 — Disaster waste
Adelaide Hills bushfire recovery — turning a regional disaster-waste challenge into a controlled recovery program
- Client / project
- Zero Waste SA — Adelaide Hills (Cudlee Creek) bushfire waste recovery program, January to May 2020
- Mike’s role
- Lead operational role: program design, contractor and stakeholder coordination, hazardous-material controls and on-ground delivery
- Challenge
- Clearing hundreds of fire-affected properties safely and lawfully, at speed, with asbestos, chemicals and CCA-treated timber spread across a working agricultural landscape
- Work undertaken
- Asbestos identification and removal process, temporary transfer arrangements, bulk-container deployment, landholder instructions and safety kits, transport configuration, separate protocols for intact posts, burnt timber and contaminated ash
- Result
- Approximately $3.68 million program: ~72 complete house demolitions and removals, 350+ partial clearances, more than 60% of removed material recovered or recycled

The emergency
The Adelaide Hills fires left a densely settled rural landscape — homes, sheds, vineyards, orchards and small holdings — covered in burnt building material, collapsed structures, damaged fencing and residues that could not simply be pushed into a heap and buried. Residents were displaced, insurers and councils were working to different timelines, and the practical task of clearing property after property had to begin before the fire ground had fully cooled.
Disaster waste is not ordinary waste. It arrives all at once, it is mixed, and it carries hazards that are invisible until someone looks for them. Asbestos cement sheeting fractures and scatters when it burns. Household and farm chemicals rupture. CCA-treated timber posts — the backbone of every vineyard and fence line in the district — concentrate copper, chromium and arsenic into the ash left behind. Every one of those problems had to be solved while people were trying to get back onto their land.
The operational challenge
The program had to move quickly without creating a second environmental problem. That meant reconciling several pressures at the same time: the safety of contractors and landholders; the regulatory obligations attached to asbestos, chemicals and contaminated soils; the limited capacity of receiving facilities; the distances involved in moving bulk material out of the hills; and the reasonable expectation of residents that their properties would be cleared properly, not just cleared.
It also had to be auditable. Public money was being spent on private land, so every property, every load and every disposal or recovery destination needed to be documented in a way that would stand up to scrutiny afterwards.


Mike’s role
Mike led and coordinated the operational side of the program. That covered the design of the clearance methodology, the engagement of demolition, transport and hazardous-material contractors, liaison with the regulator and the program’s government client, and direct dealings with landholders on the properties themselves. The role sat deliberately between the office and the site: writing the protocols, then standing on the ground while they were applied and adjusting them where reality demanded it.
The system developed
An asbestos identification and removal process was designed and implemented so that suspect material was assessed before machinery touched it, and removed under controls rather than discovered mid-demolition. Chemicals and other hazardous wastes were segregated, containerised and directed to lawful receiving points.
Temporary transfer arrangements were established so that trucks were not making long, part-empty runs out of the hills. Bulk containers were deployed into vineyards and onto properties, allowing material to be separated at the point it was generated — the single most effective way to lift recovery rates on a job of this kind. Landholders received written instructions and safety kits so they could participate safely rather than being kept at arm's length from their own land.
The CCA-treated timber stream was handled as a dedicated system in its own right. Intact posts, burnt timber and contaminated ash were each managed under separate protocols, with different handling, containment and destinations. That component alone involved around 132 bulk-bin movements and the recovery of approximately 164 drums of contaminated ash — material that, left in place, would have remained a long-term contamination liability across productive agricultural soil.


Measurable outcomes
- Approximately $3.68 million program delivered between January and May 2020.
- About 72 complete house demolitions and removals.
- More than 350 partial house, property and shed clearances.
- An asbestos identification and removal process designed and implemented.
- Chemicals and other hazardous wastes managed and lawfully disposed.
- More than 60% of the waste removed recovered or recycled.
- A dedicated recovery system for fire-damaged CCA-treated posts and contaminated ash.
Lessons for future disaster recovery
Recovery rates are decided in the first week, not the last. If separation is designed into the clearance method — containers on site, protocols agreed, contractors briefed — a disaster-waste program can recover the majority of what it removes. If separation is left until material reaches a receiving facility, it is already too late and the default becomes landfill.
The second lesson is that hazardous material must be assumed, not discovered. Building the asbestos and CCA controls into the front of the process kept people safe and kept the program moving. The third is that landholders are participants, not obstacles: given clear instructions and the right equipment, they made the program faster and safer.













